02.11.2009
SISIMIUT HYDRO ELECTRICAL POWER PLANT, IMPORTANT MILESTONE WAS REACHED 31.OCTOBER 2009:
ELECTRIFICATION OF THE TRANSMISSIONLINE: Saturday 31th.October the 27 km Transmissionline was powerized for the first time from Sisimiut Power Plant to the town of Sisimiut. This was a part of the testing and commissioning of the Power Plant´s equipment. Generator No.2 has now been fully commissioned and has passed the final exams. Generator No.1 is still in the final commissioning and is scheduled to finish the commissioning within a few days.
According to schedule, the three week trial electrical production of the 15 MW Hydro Electrical Power Plant will start after the final commissioning, before middle of November 2009. The Power Plant is scheduled to be delivered to the client Nukissiorfiit in December 2009.
|