Blönduós – waste land-fill

Blönduós – waste land-fill

CategoryOlder Projects
Investor Name:
Published Date:
January 1, 1970
Location:
Value:
Architecture:
Protocol
image_pdfimage_print

The project involves in digging, forming and finishing a special burial chamber for mixed waste for Blönduós. This will  take over from the first burial chamber part I, which is rapidly filling up. New burial chamber is southeast of the current burial chamber. The project involves the displacement of material from the chamber to the newburial champer within the site.  Completion of the burial chamber with the necessary gaskets, leachate pipes in the bottom, as well as sewer piping above the gate and bottom. All content in the drainage layer, drain embankment and sand.

Key figures:

  • Transfer of material- Sand 45,000 m3
  • Transfer of material – Clay 240,000 m3
  • Drainage layer 7,200 m3
  • Collection pipes 1,100 m
  • Soil fabric 8,850 m

Buyer:

  • Norðurá bs

Period:

  • July 2016 – December 2016

Developers:

ÍSTAK’s Role:

  • Main Contractor