Búrfell II – Trench

Búrfell II – Trench

CategoryWork in progress
Investor Name:
Published Date:
January 1, 1970
Location:
Value:
Architecture:
Protocol
image_pdfimage_print

The project – Búrfell | Trench – involves in digging and exploding for a 400 m long trench for a new inlet for the power plant Búrfellsvikrjun.

Key figures:

  • Digging 34.500 m3
  • Dredging, bulk 7.500 m3
  • Rock excavation above water 76.000 m3
  • Rock excavation under water 18.000 m3
  • Presplitt 15.000 m3
  • Rock bolts 3.600 pcs
  • Concrete injection 1.000  m3

Buyer:

Period:

  • April 2016 – april 2018

Developers:

Monitoring of the implementation:

ÍSTAK’S Role:

  • Subcontractor